Pharmaceutical

Scitra

ROModifications

2024

Year

Scitra

Scitra engaged MIDEX to modify and upgrade the Reverse Osmosis (RO) water station at its Scitra facility in 6th of October City.

The challenge

The existing RO water station needed process and capacity modifications to keep pace with production demand while maintaining pharmaceutical water-quality standards.

Our approach

MIDEX assessed the RO skid and distribution loop, engineered the required modifications, and executed the upgrade with minimal downtime to the water system.

Project scope

RO Water Station Modifications. Location: 6th of October City. Year of implementation: 2024.

Key deliverables

  • RO system assessment and modification design
  • membrane and skid modification works
  • piping and instrumentation updates
  • commissioning and performance verification

Outcome

The upgraded RO water station now delivers consistent, specification-compliant purified water output to support Scitra's ongoing production at the site.