SPIMACO selected MIDEX to deliver a Purified Water (PW) RO-RO plant at its SPIMACO facility in Borg Al Arab City.
The challenge
The site needed a new-generation Purified Water plant, built on a double-pass RO configuration, sized to its production water demand.
Our approach
MIDEX engineered, supplied and installed the RO-RO purified water plant, integrating it with the site's utilities and validating its output against USP/Ph.Eur specification.
Project scope
PW (RO - RO) plant - 2500 L/hr. Location: Borg Al Arab City. Year of implementation: 2025.
Key deliverables
- PW plant engineering and supply
- double-pass RO installation
- piping and controls integration
- commissioning and performance qualification support
Outcome
The new PW (RO-RO) plant supplies SPIMACO with a dependable source of purified water at the site.