Cons Korra engaged MIDEX to install a pure steam pipeline network at its MEVAC5 facility in Al-salheia City.
The challenge
The site required a pure steam distribution network engineered to hygienic design standards and capable of maintaining steam quality to point of use.
Our approach
MIDEX designed the pure steam routing, selected suitable materials and insulation, and installed and tested the network to pharmaceutical standards.
Project scope
Pure steam pipe line network. Location: Al-salheia City (MEVAC5 facility). Year of implementation: 2025.
Key deliverables
- Pure steam network design
- piping fabrication and installation
- insulation
- pressure testing and documentation
Outcome
Cons Korra now benefits from a validated pure steam distribution network at MEVAC5.